US data center buildout

21 AI data center projects across 13 states, from the Stargate campuses to the Colossus cluster in Memphis to Project Rainier in Indiana. Filter by state or search by project, company, or city. Investment figures are reported or announced amounts, and statuses change as construction proceeds.

21
projects tracked
14
states
6
operating or partially operating
7
under construction

Project spotlights

Four campuses that define the buildout

Deeper looks at the four most consequential projects in the table, all facts sourced.

Stargate flagship campus, Abilene, Texas

OpenAI, Oracle, SoftBank | $500B program (multi-site) | Operational, final building topped out

The first Stargate site to come online is being developed by Crusoe on the Lancium Clean Campus and leased to Oracle and OpenAI. Eight buildings are planned across about 4 million square feet with 1.2 GW of total power capacity. Construction has run since July 2024, and the first NVIDIA GB200 racks arrived earlier this year. Reporting describes plans for OpenAI and Oracle to deploy 450,000 GB200 GPUs at the site.

The first two buildings, 980,000 square feet supporting 200MW+ of IT load, are operational and used by Oracle Cloud Infrastructure for OpenAI. Crusoe says about 7,000 electricians, construction workers, and skilled tradespeople come to Abilene every day. The second phase, six more buildings, is expected to complete in mid-2026.

Sources: Data Center Dynamics, Intuition Labs

Colossus cluster, Memphis, Tennessee and Southaven, Mississippi

SpaceXAI (xAI) | ~$18B in GPUs reported Jan 2026 | Operational and expanding

Colossus 1 was built at a former Electrolux plant in South Memphis: roughly 100,000 NVIDIA H100 GPUs went live in mid-to-late 2024 after a 122-day build, later joined by H200 and early B200 systems. Colossus 2, branded Macrohard, sits at 5420 Tulane Road in Whitehaven; its first major cluster of about 110,000 GB200-class processors and roughly 210 MW came online around January 2026 after a reported 91-day build.

By late September 2026, 440,000 GB300 GPUs were in use with 660,000 more expected by the end of 2026. In May 2026, Anthropic agreed to rent essentially all compute capacity at Colossus 1, and in June 2026 Google agreed to rent about 110,000 GPUs for $920 million per month from October 2026 through June 2029. Power comes from behind-the-meter gas turbines in Southaven plus a permanent roughly 1.2 GW plant permitted in March 2026. The cluster targets about 2 GW of total compute across the Memphis area.

Sources: Wikipedia: Colossus (data center), BigGo Finance

Project Rainier AI campus, New Carlisle, Indiana

AWS / Anthropic | $11B | Operational since late 2025

Project Rainier is an $11 billion gigawatt-scale campus built by AWS around nearly 500,000 of its custom Trainium2 AI chips, with plans to scale beyond one million. Operational since late 2025, it trains and deploys Anthropic's Claude models outside the NVIDIA-dominated GPU market. Amazon has invested $4 billion in Anthropic, and the campus is the physical form of that partnership. The project is scaling toward 2+ GW of capacity.

Sources: Neowin, i10x.ai

Hyperion AI training campus, Richland Parish, Louisiana

Meta | $50B+ expanded scope (original $10B announcement Dec 2024) | Under construction

What began as a $10 billion proposal announced in December 2024 has grown into a more than $50 billion development spanning nearly 10 million square feet on about 3,650 acres. At full scale, Hyperion is expected to reach 5 GW of computing capacity, which would make it the largest data center in Meta's global fleet and one of the largest ever built. Meta says the project will employ around 7,500 workers at peak construction and support 1,000 permanent jobs once operational. Power is planned from Entergy plants targeting late 2028.

Sources: Sue Data Centers, Breakthrough News

Advertisement

The full table

All 21 projects

Search or filter. Status counts right now: 1 announced, 5 in development, 1 opening, 6 operating, 1 other, 7 under construction.

21 of 21 projects shown

ProjectCompanyStateCityInvestmentStatusSources
Stargate flagship campus OpenAI, Oracle, SoftBank TX Abilene $500B program (multi-site) Operational, final building topped out; eight buildings, 1.2 GW planned capacity Data Center Dynamics
Intuition Labs
Stargate site (Shackelford County) Oracle TX Shackelford County Part of $500B Stargate program In development One Year Ago in AI
Stargate site (Milam County) SoftBank TX Milam County Part of $500B Stargate program In development One Year Ago in AI
Stargate site (Lordstown) SoftBank OH Lordstown Part of $500B Stargate program In development One Year Ago in AI
Stargate site (Doña Ana County) Oracle NM Doña Ana County Part of $500B Stargate program In development One Year Ago in AI
Colossus supercomputer cluster SpaceXAI (xAI) TN Memphis ~$18B in GPUs reported Jan 2026 Operational and expanding; ~2 GW total compute target across the Memphis area cluster Wikipedia: Colossus (data center)
BigGo Finance
MACROHARDRR data center SpaceXAI (xAI) MS Southaven Over $20B corporate investment reported In development; ~1.2 GW gas turbine power plant approved Tech Research Online
Wikipedia: Colossus (data center)
Project Rainier AI campus AWS / Anthropic IN New Carlisle $11B Operational since late 2025; ~500,000 Trainium2 chips, scaling toward 2+ GW Neowin
i10x.ai
AWS Canton campus AWS MS Canton Part of $10B two-campus Mississippi program Under construction; first section operational in 2025 Measured AI
About Amazon
AWS Ridgeland campus AWS MS Ridgeland $11B expansion announced 2025-2026 Under construction; expansion announced April 2026 Measured AI
Clarion Ledger
Hyperion AI training campus Meta LA Richland Parish $50B+ expanded scope (original $10B announcement Dec 2024) Under construction; 5 GW planned compute capacity; Entergy power plants targeting late 2028 Sue Data Centers
Breakthrough News
El Paso AI data center campus Meta TX El Paso Over $10B Announced July 2026; 1 GW planned; capacity online starting 2028 TxEDC / Business in Texas
New Albany campus (Prometheus supercluster) Meta OH New Albany $1.5B+ (Prometheus expansion) Operating campus with 2026 rapid-deployment expansion targeting the Prometheus cluster Neowin
Next Big Future
Jeffersonville data center Meta IN Jeffersonville $800M Operational in 2026; Meta's 18th US data center Business Facilities
Project Cosmo Meta WY Cheyenne $800M Under construction; expected 2027 MCG Invest
Montgomery data center Meta AL Montgomery $1.5B Opening 2026 MCG Invest
Kuna data center Meta ID Kuna $800M Operational since 2025 MCG Invest
Vaucluse data center Meta SC Vaucluse $800M Under construction; expected 2027 MCG Invest
West Memphis AI data center campus Google AR West Memphis $4B Under construction since Oct 2025; ~1,100 acres When In Your State
Mount Pleasant AI data center hub Microsoft WI Mount Pleasant $7B+ committed ($13B proposed expansion) First facility (Fairwater) opened early 2026; 15 additional centers approved Jan 2026 AInvest
Introl
Licking County data center expansion Microsoft OH Licking County (New Albany, Heath, Hebron) $1B Under construction after restart; groundbreaking Feb 2026 Construction Review Online

Source links open the original reporting. This table tracks announced projects; completion dates and capacities are as reported at access time, October 16, 2026.

Questions

Buildout FAQ

Answers grounded in the sourced table above.

Which project is the biggest?

It depends how you measure. The largest single campus disclosed is Meta's Hyperion in Louisiana: 5 GW of planned compute capacity and a scope expanded to more than $50 billion. The largest program is Stargate: a $500 billion joint venture targeting 10 GW of US AI compute across multiple campuses. Both are announced figures, not completed capacity.

What does gigawatt (GW) mean for a data center?

It is the planned power capacity of the campus, the ceiling on how much electricity the compute can draw. AI training clusters draw enormous, steady power, so projects are sized in gigawatts the way older data centers were sized in megawatts. Disclosed figures here run from about 1 GW to 5 GW per campus.

Why are so many projects in Texas, Ohio, and Mississippi?

Those three states host 10 of the 21 tracked projects: Texas has four (Abilene, Shackelford County, Milam County, El Paso), Ohio has three (Lordstown, New Albany, Licking County), and Mississippi has three (Southaven, Canton, Ridgeland). The dataset records locations; it does not attribute causes. Commonly cited factors in the linked reporting include available land, power access, and state incentive packages.

How current is this table?

All data was accessed on October 16, 2026. Construction statuses change as projects proceed: campuses listed as under construction may open, and announced projects may be delayed. Investment figures are reported or announced amounts.

Do the source links open the original reporting?

Yes. Every row links the reporting each claim came from, so you can verify dates, figures, and statuses yourself. The full list of unique sources is on the about page.